2026-07-14·Clear 74°F·15.5h logged
Kitchen fully stripped. Backer wall exposed. Ready for framing tomorrow.
Production: 120 sqft demoed
Crew
Carlos Mendez, Devon Park
Deliveries
Dumpster drop — Bay Waste 20yd
Safety
PPE compliant. Dust barriers up.
Issue: Existing plumbing not centered — will need offset. Notified plumber.
Summary
Day 1 demo tracking on plan (~15.5h against 24h budget). Plumbing offset discovered — minor scope impact. Recommend brief PM check-in before framing to confirm rough-in dimensions.
Posted by Carlos Mendez · 7/14/2026, 5:15:00 PM